House renovation steps detailed process

After purchasing a new home and accepting it, one more important thing came one after another - decoration. In addition to the purchase of refined decoration rooms and second-hand housing, the buyers bought the hands are the embryonic embryo room, decoration has become a major event after the purchase. So what is the renovation of the house ? Let's take a look with Xiaobian.

House renovation steps

1, for start-up procedures - 2, self-measurement - 3, pre-design - 4, the main demolition - 5, door manufacturers door measurement - 6, the first measurement of the cabinet - 7, hydropower reform - 8 , toilet waterproofing - 9, main material approach - 10, carpentry - 11, tiling (installation windowsill, floor drain) - 12, install the hood - 13, cabinets for the second measurement - 14, brush the wall Top coat -15, kitchen ceiling -16, gas -17, cabinet installation (install sink, gas stove) -18, wooden door installation -19, floor installation -20, paving wallpaper - 21, Radiator installation - 22, switch socket installation - 23, lighting installation - 24, hardware sanitary installation - 25, curtain rod installation - 26, pioneering cleaning - 27, furniture approach - 28, home appliances Installation - 29, home accessories - 30, moving.

House renovation steps detailed process

1. Pre-design: In the preliminary design, it is necessary to make a detailed measurement of your own room. Do not be lazy. It is best to measure it yourself. The contents of the measurement mainly include: a. The area covered by the decoration process. In particular, tiling area, wall paint area, wallpaper area, floor area; b, clear the main wall size. In particular, it is necessary to design the wall size of the furniture later.

Remind everyone, do not forget to go to the property before the start of construction formalities, pay a decoration deposit.

2. The main part of the house renovation process is: At the construction stage, the main demolition reform is the first one on the project. It mainly includes the demolition of walls, walls, spade walls, demolition of heating, change of steel windows, and so on. When the main body is dismantled and reformed, it is to put the framework of the construction site first.

3, hydropower reform: Before the water circuit transformation, the main structure demolition and reform should be basically completed. Between the two stages of hydropower reform and main body demolition, the first measurement of cabinets should also be carried out. In fact, the so-called cabinet first measurement has no actual content, because the wall and the ground are not processed, the cabinet designer can not give a specific design size, but only for the developer reserved water inlet, hood socket Location, make some suggestions.

Mainly include: a, to see if the position of the hood socket affect the installation of the hood; b, look at the location of the water meter is appropriate; c, see if the location of the inlet is convenient for the installation of the sink. For the first measurement of the cabinet, it can be completely done by itself. After the waterway is completed, it is best to do the waterproofing of the bathroom. The kitchen does not generally need to be waterproof.

Prior to the start of renovation, the arrival time of main materials, such as tiles and large core boards, should be after the hydropower reform. Because the circuit modification involves ground slotting, if tiles or large core boards are improperly positioned, it is troublesome for workers to move in and out.

4. Carpentry: Carpenters, bricklayers, and oil workers are the “three brothers” in the construction process. The basic order of appearance is: tile-wood-oil. The basic appearance principle is - who is dirty and who is the first. "Who is dirty? Whoever is above" is also one of the basic principles that determine the order of home improvement.

In fact, carpentry activities such as installing standpipes, making decorative ceilings, and attaching plaster lines can be considered in a sense as a detailed link of the main demolition and reform. They themselves do not conflict with the transformation of water circuits, and sometimes they still need some. Cooperate.

5, tiling: If the workers are too busy, the foreman will generally let the “wooden cock” enter the court when the “tile boss” is not over. This is normal, because there is no conflict between the two.

In the process of tile work, it also involves the following three steps of installation: a. The installation of the door stone and marble window sill. The installation of the door stone can be done together with the paving tiles, or after the paving tiles, the installation of the marble window sill is usually done after the window cover is done. The marble worker will prepare the glass glue, and the marble and the window cover are sealed with glass glue. Now. b. Installation of floor drain. The floor drain is the first one to appear in the home improvement hardware because it needs to be installed together with the floor tile. It should be early to buy a floor drain. c. Installation of hoods. The hood is the first appearance of the appliance. After the kitchen tiles are laid, you can consider installing the hood. The bricklayers leave the floor. At this time, the cabinet can be measured for the second time. Accurately, after the wall tiles have been attached and the hood is installed, the cabinet can be measured for the second time.

6, brush wall paint: oil workers approach, mainly to complete the basic treatment of the wall, brush finish, wood furniture hit the furniture painting and so on. To prepare a wallpaper, you only need to let the oilworker do the grass-roots work on the walls of the wallpaper. As to whether or not to leave the last time to finish the paint, personally feel that this problem is not necessarily too true, my experience of decoration, the significance of leaving paint again is not great, because the back of the operation is no more dirty than the paint.

The general understanding of the decoration is only the decoration of the "construction part", in fact, the decoration of the "installation link" is also the focus of decoration. If the "design link" is to "conceive" the look of our future home, then the "construction link" is to "package" our home, and really say that "home-made" homes are almost all in the "installation phase."

7, kitchen ceiling: cabinet ceiling as the installation of the first team, or in the continuation of the home "packaging." At the same time as the kitchen ceiling, the kitchen's moisture-proof ceiling lamp and exhaust fan (Yuba) should have been bought. It is best to install ceiling lights and exhaust fans (bath heaters) at the same time, or to leave the heads and openings.

I believe that the professional construction, believe that the manufacturers of the installation level, believe that the product line of production operations, mostly compared to the decoration of the team of workers slightly better. Decoration is like a game. The bet is the craft of the workers. In fact, each part of the decoration is very independent, accurately grasp the choice of materials, master some simple construction process, handle the relationship between workers, etc. This is the key.

Decoration, quality is always ranked first, is the main contradiction, is the principle.

8, kitchen cabinet installation: after the ceiling is over, you can install the cabinet about the door. If it goes well, one day can be completed. At the same time there is a sink (can not include water and water parts) and gas stove, the best coordination of the property before the installation of the gas pass, because the gas stove installed after the need to test gas.

9. Door installation: On the second day of cabinet installation, as soon as the wooden door measurement is completed more than one month ago, it is now possible to install it. If it goes well, it is also the time of the day. The hinges, door locks, and suctions to be installed at the same time when the door is installed. Prepare related hardware in advance.

If you want the wooden door manufacturers to install window covers and gargles, they should be measured together when the wooden door manufacturers measure them, and they should be installed on the same day that the wooden door is installed. At the same time, the installation time of the marble window sill should be considered wrong. After installation.

The production period of wooden doors is generally one month. Therefore, in order to make the construction period close together, the size of the door opening should be measured as soon as possible after the main demolition is completed. With regard to the handling of door openings, we must pay attention to the fact that if the height of the door opening is inconsistent, workers need to be treated as if they are of equal height.

10. Floor installation: The floor can be installed on the second day of wooden door installation. If it is successful, it is also a day. The following problems need to be noted in the floor installation: a. Before the floor is installed, it is best to let the manufacturers survey whether the ground needs to be leveled or partially leveled. Some decoration companies or renovation teams will suggest leveling or local leveling to the floor. The survey shall prevail; b. Before the floor is installed, the floor of the home's paving floor should be cleaned, and the ground must be kept dry. Therefore, do not use water during the sweeping process. c. When the floor is installed, the cutting of the floor must be in the corridor.

11, paving wallpaper: In the second floor of the installation, clean up, wallpaper can be paved, and smooth, the same is the time of day. If conditions permit, on the day of paving the wallpaper, the floor should be protected; if it is not conditional, it is okay to clean the leftover wallpaper glue on the floor to the original cleaning. Before paving the wallpaper, try to "don't have anything" on the wall.

12. Radiator Installation: On the second day after the wallpaper is paved, replacing the radiator or dismantling the radiator can literally place the radiator on the wall. The same is the time of day. Wooden door - floor - wallpaper - heat sink, this is a generally recognized correct installation order, first install the wooden door is to ensure that the baseboard of the floor can be closely integrated with the door of the wooden door cover; after loading the wallpaper is mainly because of the floor The installation is more dirty, more dust, and serious wallpaper pollution. The final radiator is installed because only the wallpaper on the wall can be installed to install the radiator.

In addition, I repeatedly said that "a day's time", "a day" is not a long time for the entire renovation, so even if there is no installation conflict, such as cabinets and doors, try not to book two installations at the same time in a day Especially for these "big things" mentioned above, because the installation is very critical for these "big things", it is better to focus on one site, rather than "use one." Learn to comfort yourself - that day is not bad.

13. Switch socket installation: There should be a detailed understanding or record of the number of switches and sockets in the house and the location of the home, especially for wallpapers. Sometimes wallpaper workers are not responsible for wallpapers. He also doesn't use a wallpaper knife to mark holes in your switch socket. So, you need to know what you think.

14, lighting installation

15, hardware, sanitary ware installation, before buying a good water pipe fittings, bathroom accessories, toilets, drying racks, etc., are also installed. After those “big things” were installed, the family was still “cold”. After the fixtures and hardware were installed, the family “lived”.

16, curtain rod installation

17, pioneering cleaning

18, furniture approach, on the purchase time of furniture, my suggestion is that the earliest to be completed after the transformation of the water circuit, so that the basic size of the choice of furniture, the heart of a few.

19, appliance approach

20. The last step of home accessories, home accessories, and home decoration has been changed from decoration to decoration, including the installation of curtains that belong to the home accessories link. As for the purchase of curtains, it is best to order furniture to avoid style conflicts. Home accessories also include considerations such as buying some green plants, wall paintings, handicrafts, etc.... In short, after your stay, you are free to play.

The above detailed process on the renovation of the house is simple for you to introduce here, and I hope to help you! For more information, please visit this website. Stay tuned.

Renovation Steps House Decoration Home Furnishing Bathroom Tiles Home Decor Tiles Kitchen Tiles ld Tiles Floor Tiles Decoration Home